Highlights of the Relocation and Installation of FEROS to the ESO/MPI 2.2m telescope
Disassembly, Relocation and Re-Assembly & Alignment -- October 6 - 11, 2002
The Disassembly, Relocation and Re-Assembly & Alignment was completed as planned and in quick time with no problems. Furthermore as a result of the realignment, the instrument is possibly in better shape than prior to the move.During alignment tests the shutter was noticed to be malfunctioning. A modification to the release cable by A.Kaufer remedied the problem.
Disassembly, Relocation and Re-Assembly & Alignment was lead by A.Kaufer and assisted by A.Gilliotte, I.Saviane, J.Pritchard, G.Ihle and a large team from MEC.
More details to come...
FEROS/WFI Adapter and Calibration Unit Installation -- October 16 - 22, 2002
Final Opto-Mechnical/Electronic integration, testing and alignment included:- Re-figuring of adapter tower
- Replacement of M3 motor with a smaller barrel model
- Extension of Fibre Head carriage
- Replacemet of Fibre Head/Fibre Head Viewer TCCD lense with a longer focal length.
- Modification of Sliding Calibration Selection Mirror mounting.
- Replacement of tachometer wire after being severed during an install of WFI.
- Preparation of Science fibres
- Alignment of Science fibres
- Alignment of Calibration fibres
More details
to come...
FEROS/WFI Adapter and Calibration Unit Modifications -- October 27-November 13, 2002
The following modifications were made to the FEROS/WFI Adatper and Calibration Unit during the period October 27 to November 13, 2002:- Extension of the Adapter tower.
- New science fibre ferules made.
- Preparartion of science fibres with new ferules.
- FFHV TCCD/filter system modified so that filter and CCD move as one unit.
- Large format TCCD installed on a temporary basis (previously a small format TCCD was installed).