**** NACO-SV mtg - July 5 at 14:00 (Garching, Rm 231) **** Agenda: ------- 14:00-14:15 Alvio: Updated timeline for SV observations 14:15-15:00 Wolfgang: Report on the latest NACO commissioning 15:00-15:15 Wolfgang/Lowell Status report on NACO Observing Templates 15:15-18:00 Around the table discussion on the following specific points: a) Assign priorities to SV observations: 1 - first priority! 2 - all efforts should be made to carry out observations 3 - observations should be carried out if SV telescope time is still available 4 - back-up plan in case higher priority targets do not meet observing constraints 5 - rejected SV target b) Define tasks and procedures to make OBs for each SV program c) Make specific plans about SV data reduction d) Handling of specific data sets (e.g. selected commissioning data and Galactic Center observations carried out in May)